I need to take a large MS project plan and import to visio. To be able to
see smaller cuts of it I planned on configuring the timeline after importing
it and then putting in only the dates for each quarter. I would need to make
multiples of these. But, when doing that all the other tasks end up stacking
on the last day of the quarter no matter when they happen in the future. Is
there a way so they don't get pulled in? Or is there a way to import only
that section instead of the whole project?