Timephased actual work in Activities

G

Gil

Hi,
In Project Server 2007, After I assign resources to tasks in an
activity plan, the resources submit actual work, I accept it and
publish the activity.
At the end of the month I want to know how much work was done by each
resource for the month. I could not find a way to do that in PWA,
without using data analysis.
Thanks for any help,
Gil
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top