Can MS Project display timephased values of remaining earned value ? eg task
has fixed costs only of £100 and duration is 5 months ie £20/month, but %
complete at end month 3 is only 48%, so BCWP is £48. Remaining earned value
is therefore £52 ie £26 per remaining 2 months. How can I show this in the
Task Usage view ?