Can MS Project display timephased values of remaining earned value ? eg task
has fixed costs only of £100 and duration is 5 months ie £20/month, but %
complete at end month 3 is only 48%, so BCWP is £48. Remaining earned value
is therefore £52 ie £26 per remaining 2 months. How can I show this in the
Task Usage view ?
 
J

Jim Aksel

Baseline Cost-cumBCWP is remailing EV. However, there is no way to include a
custom formula in the time phased portion of the task usage view. You can do
it on the left side.

I think you are going to have to export to Excel to do this. My first
thought was to try to calculate the value into a spare cost column and then
copy that over to one of the spare baselines (which you can show on the Task
Usage View). However, the custom fields do not work well with time phased
data.




--
If this post was helpful, please consider rating it.

Jim Aksel, MVP

Check out my blog for more information:
http://www.msprojectblog.com
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top