Timephased tracking method issue after June CU

G

Gil

Hi,
We had an activity, which we have converted (before installing SP2) to
a regular project.
Users were able to report progress in the time-phased grid We force
all PM to use "Hours of work done per period" method).
After upgrade to SP2+ JuneCU, Users are not able to input timephased
data in My task grid for this project (they can for others).
I`m confused: Shouldn`t June CU fix this issue? And if this is our
situation, does this mean we havn`t applied the CU correctly?
Thanks,
Gil
 
S

Skip W

Gil,

I had a similar issue and the problem was after converting the activity to a
project the project was really tracking in Percent of Work Complete. To fix
it I cleared the
force option on Server, started Pro and opened the project, set
Options->Collaborate to "Hours of work done per period" and published it.
Then I turned the force option back on in Server. Hope this helps.
 
G

Gil

Gil,

I had a similar issue and the problem was after converting the activity to a
project the project was really tracking in Percent of Work Complete.  To fix
it I cleared the
force option on Server, started Pro and opened the project, set
Options->Collaborate to "Hours of work done per period" and published it. 
Then I turned the force option back on in Server.  Hope this helps.





- Show quoted text -

Skip W, Thanks for your quick response, and the great sollution. It
worked great!
Gil
 
S

Seth Gillespie

We have confirmed this "fix" after our SP2 + Apr CU upgrade - for
those plan that were effected. However we do not use the "force
option."

Regards,
 