G
Gil
Hi,
We had an activity, which we have converted (before installing SP2) to
a regular project.
Users were able to report progress in the time-phased grid We force
all PM to use "Hours of work done per period" method).
After upgrade to SP2+ JuneCU, Users are not able to input timephased
data in My task grid for this project (they can for others).
I`m confused: Shouldn`t June CU fix this issue? And if this is our
situation, does this mean we havn`t applied the CU correctly?
Thanks,
Gil
We had an activity, which we have converted (before installing SP2) to
a regular project.
Users were able to report progress in the time-phased grid We force
all PM to use "Hours of work done per period" method).
After upgrade to SP2+ JuneCU, Users are not able to input timephased
data in My task grid for this project (they can for others).
I`m confused: Shouldn`t June CU fix this issue? And if this is our
situation, does this mean we havn`t applied the CU correctly?
Thanks,
Gil