Timephasing of Cost1

A

Andy Greenhalgh

I've set up my projects using Cost1 fields to allow me to state one as
revenue, another as capital expenditure, another as benefit etc.

The problem is that I'm wanting a view that can timephase this over fiscal
year to aide in scenario planning.

At the moment I've gone into Task Usage and can timephase my Cost but the
'Details' availble don't include the custom costs.

Does anyone know a way that I could include them in the timephasing?

Thanks

Andy
 