Timescale in Project Centre

A

Apost

At the moment the time scale in Project Centre on Project Web Access displays
weeks and days wich is to small a scale for what I need. I know how to change
the time scale in Microsoft Office Project Profesional but I do not know how
to change the timescale for people viewing projects on Web Access.

Thank you for you time.
 
R

Ray McCoppin

Each user can set the timescale in the project center view using the
magnifiying glass Plus and minus. PWA will remember using a cookie from IE
how to set the timescale for that user.

You can modify the PWA asp page to defualt to something other than that is
in the cookie.

Hope this helps.
 