Timescale/MSP 2003

J

JCG

Under Admin > Customize Project Web Access > Gantt Chart Formats I cannot
find where I can change the timescale for the Gantt Charts. I've been able
to change the bar styles, however I can't find anywhere/link that allows me
to change the timescale. Can anyone help.
 
G

Gary L. Chefetz [MVP]

JCG:

In any Gantt chart display in PWA, there are + and - icons on the toolbar
above the grid. Click these to change the timescale. Unfortunately this must
be done on presentation and can't be preset in the build view process.
 
C

CJR

Perhaps this does satisfy the posted question , however I was hoping to find
a different answer:

When I set up my project templates I configured the timescale with three
tiers: top tier = "YYYY Month" on a monthly cycle, middle tier = "annual week
#" on a weekly cycle, bottom tier = "MM-DD" for the monday of the weekly
cycle.

Since our company does most of its planning by the week number it is vitally
important to be able to relate the milestones to weeks. Unfortunately, in
SWA, it seems that the timescale for display has been arbitrarily decided
upon as a two-tier, weekly/day name display and I can find no way to change
it. This reduces the usability of the tool for us somewhat. Is there any
way to make the SWA timescale display match the format in the template(s)?

Thanks
 