Timescale

D

DYCC

Hello,

I have a 3 tier gantt chart set up - Month, Week, and date of week start.
Current date is September 9, however my project start was August 11. I want
August 11 to show as week 1, but curently shows week -4. The current date
line on September 9 is counting backwards showing week of September 8th as
'Week 1'. How do I change this?

Thanks in advance, and look forward to hearing from anyone that can help.

Cheers,
 
C

Colin

Hi DYCC

Go into Project - Project information
Change the start date to August 11

Colin
 