Timescaledata

B

Brian

I am looking at obtaining programmatically a summary of costs in each project
by month probably using pjtasktimescaledcost and adding the monthly task
costs together (if there is not an overall similar project level timescaled
cost method)

I wonder if anyone has any code or advice.

Am struggling and Can't seem to find any example code using
pjtasktimescaledcost

Need to do this without using cube/project server and project usage views etc

Thanks

Brian
 
J

Jan De Messemaeker

Hi

Use the timescaledata method (look up the help)
It can be used against the projectsummary task
HTH
 
B

brian

Jan

I hadn't realised that this would work for the projectsummary task.

Should save me a lot of work!

Many thanks

Brian
 