J
Juan
Hi!
I have a question about using TimeScaleData in order to import some values
from MS Project to MS Excel.
I was wondering if it is possible to customize the TimeScaleUnit to make it
pic Resource.TimescaledCost and Resource.TimescaledWork half-monthly.
The aim is to be able to fill in a table in Excel which runs fornightly with
the values of scheduled costs and scheduled work hours. I havent been able to
find a predefined TimeScaleUnit.
I hope there's someone.... who can help me with this.
Thanks in advance.
I have a question about using TimeScaleData in order to import some values
from MS Project to MS Excel.
I was wondering if it is possible to customize the TimeScaleUnit to make it
pic Resource.TimescaledCost and Resource.TimescaledWork half-monthly.
The aim is to be able to fill in a table in Excel which runs fornightly with
the values of scheduled costs and scheduled work hours. I havent been able to
find a predefined TimeScaleUnit.
I hope there's someone.... who can help me with this.
Thanks in advance.