we just installed EPM 2007 Server and we did few tests. One user inseted his
done work in the timesheet. I approved it. I expect to see some updates on
the Project server. But nothing has changed. What should I do to get the
changes updated to the server?

Many thanks
ALN
 
D

Dale Howard [MVP]

ALN --

Time information that is entered in the My Timesheet page is NOT applied to
the project schedule in Microsoft Project. The user must either import his
Timesheet hours into the My Tasks page or must type the numbers manually in
the My Tasks page, and then submit the Task Update to his PM for approval.
Once approved, the hours from the My Tasks page will update the Microsoft
Project 2007 plan. Hope this helps.
 
A

ALN

Dale
many thanks,

but when i try to import tasks from timesheets (my Timesheets) into My
Tasks only a small part of the tasks are avialbel, for a seconed/onother user
even is nothing available for the specific timesheet period!!!

Any idea?
Thank you
regards
ALN
 
D

Dale Howard [MVP]

ALN --

When a user attempts to import time from the My Timesheet page into the My
Tasks page, the system only imports time for project tasks. It does not
import time spent on non-project tasks a non-working time. Furthermore, it
only imports time actually entered on a project task. So, if a user has two
tasks, he entered time on one and not on the other, the system will only
import the time for the first task. Does this explain your problem? Let us
know and we will try to help.
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top