B
Barbara G
Hi,
The timesheet actuals from resources aren't correctly showing in the
project. For example, I have a resource who put 5 hours in one of the days
and the project is showing 0 for that date. Is there something happening on
the server that could be causing the actual work to change?
Thanks,
The timesheet actuals from resources aren't correctly showing in the
project. For example, I have a resource who put 5 hours in one of the days
and the project is showing 0 for that date. Is there something happening on
the server that could be causing the actual work to change?
Thanks,