Timesheet actual work submitted against a project top level task

R

RHS

Hi,
I just wanted to verify. If actual work is submitted against a project top
level task in a timesheet, that data stays in the timesheet. It does not get
into the task updates via import timesheet. It does not show up anywhere in
the project's actual work, either in MS Project, the project tables reporting
database or the project cubes. You can see this in the timesheet tables in
the reporting database and timesheet cubes.
Thanks,
Erik
 