T
Tony Josephs
We have been using PWA and PS2k for a month now and are getting used to its
little foibles. One we can't seem to find an answer to in MS Project 2k
Inside Out or Gary's MS Project Server 2002 tome is that every time we
accept updates from timesheets back to the project plan, if the actuals are
greater than the estimates (stored in work), work is over written with the
actuals value. So we can't track what the work was before and therefore how
much we have gone over on a particular task.
Am I missing some simple setting somewhere?
We record hours of work done per day but not work remaining and I know that
this might sound stupid but we don't baseline our projects. Do we need to
get into a whole baselining thing before the estimates will stick?
Please let me know.
TIA
Tony
little foibles. One we can't seem to find an answer to in MS Project 2k
Inside Out or Gary's MS Project Server 2002 tome is that every time we
accept updates from timesheets back to the project plan, if the actuals are
greater than the estimates (stored in work), work is over written with the
actuals value. So we can't track what the work was before and therefore how
much we have gone over on a particular task.
Am I missing some simple setting somewhere?
We record hours of work done per day but not work remaining and I know that
this might sound stupid but we don't baseline our projects. Do we need to
get into a whole baselining thing before the estimates will stick?
Please let me know.
TIA
Tony