We are coming to the completion of a full EPM implementation and will use PWA
to communicate tasks to team members and receive status information back from
them. Despite trying (via modelling) different settings of the three types of
default methods of reporting tasks and different task types setting we
cannot find an elegant solution. Simply put we want to show task completion
in % and have the team members “book†time in hours (in timsheet) against
each task and track work and task overruns.
Would much appreciate any suggestions - we are convinced if the right
combination of setting we can achieve our goal.