G
ghostme
Hello guys,
I am currently undertaken a test deployment of Project server 2007 for a
client, during the business requirements gathering i found out that the users
will be practically filling in the same time they fill in the task update
page and in the My timesheet features.
The task updates is to update and track the project schedule while the
timesheets are used to report time spent on the project tasks.
What is the best way for me to configure both the task and timesheet
settings. Should i enforce the synchronization of timesheet hours with hours
reported on task update? or otherwise.
Thank you
I am currently undertaken a test deployment of Project server 2007 for a
client, during the business requirements gathering i found out that the users
will be practically filling in the same time they fill in the task update
page and in the My timesheet features.
The task updates is to update and track the project schedule while the
timesheets are used to report time spent on the project tasks.
What is the best way for me to configure both the task and timesheet
settings. Should i enforce the synchronization of timesheet hours with hours
reported on task update? or otherwise.
Thank you