K
Konstantinos Christodoulakis
Dear all,
I have the following scenario and question:
Employee1 filled-in the actual hours for Week-1 (01.01.2010-08.01.2010)
having 5 Timesheet Lines (for different tasks) and submitted them to his
TimesheetManager1.
TimesheetManager1 approved it and the whole Timesheet appears as "Approved".
QUESTIONS:
1. In which table of ProjectServer_Published database can I find the
Timesheet Approval Statuses?
2. Do the TimesheetLines having different statuses during approval workflow?
Where are they stored (as statuses) in ProjectServer_Published database?
3. ASSUMPTION: My example Timesheet has 5 TimesheetLines inside the database
and every TimesheetLine has an approval status.
Is that right?
Hope to have answer to this question.
Kind regards,
Konstantinos Christodoulakis
Senior Project Manager
I have the following scenario and question:
Employee1 filled-in the actual hours for Week-1 (01.01.2010-08.01.2010)
having 5 Timesheet Lines (for different tasks) and submitted them to his
TimesheetManager1.
TimesheetManager1 approved it and the whole Timesheet appears as "Approved".
QUESTIONS:
1. In which table of ProjectServer_Published database can I find the
Timesheet Approval Statuses?
2. Do the TimesheetLines having different statuses during approval workflow?
Where are they stored (as statuses) in ProjectServer_Published database?
3. ASSUMPTION: My example Timesheet has 5 TimesheetLines inside the database
and every TimesheetLine has an approval status.
Is that right?
Hope to have answer to this question.
Kind regards,
Konstantinos Christodoulakis
Senior Project Manager