MaryTech
At the end of June we went live with Project Server 2003. Since our go live
there are 2 questions I cannot seem to find the answer to pertaining to
timesheet approval. They are:
1) Even though a resource selects update all when submitting their
timesheet, not all 40 hours appears on the Approve Timesheet view. If the
manager goes into View resource assignments they can verify the resource has
submitted 40 hours. The timesheet behavior appears to be random. Can anyone
explain this behavior?
2) In a timesheet some of the entries appear to be colored coded in red,
some in blue and others in black. Can anyone provide a definition for this
color coding?
there are 2 questions I cannot seem to find the answer to pertaining to
timesheet approval. They are:
1) Even though a resource selects update all when submitting their
timesheet, not all 40 hours appears on the Approve Timesheet view. If the
manager goes into View resource assignments they can verify the resource has
submitted 40 hours. The timesheet behavior appears to be random. Can anyone
explain this behavior?
2) In a timesheet some of the entries appear to be colored coded in red,
some in blue and others in black. Can anyone provide a definition for this
color coding?