Timesheet Approval Error

B

Brian Duper

So we have a fairly vanilla configuration of PS server, and a resource
manager is getting this error when attempting to approve a timesheet (see
below).

We do have an RBS but the Resource Manager group has the "My Org" category,
so they should be able to approve right? Not saying this is an RBS
permission issue, but just pointing it out. On that note, if the Resource
Manager group has the "My Org" category, is it necessary, or harmful, if the
they have the other categories too, "my direct reports, my resources, etc,
etc".

Anyone shed any light?

Thanks- Brian



<?xml version="1.0" encoding="utf-16"?>
<errinfo>
<general>
<class name="Resource 850e4d88-7597-47eb-a626-b57b4217923a is listed as
next approver for timesheet 29451a44-0482-4a86-a370-122b433ad5d6. Timesheet
owner or previous approvers cannot be approver">
<error id="3205" name="TimesheetInvalidApprover"
uid="5b312d64-086d-4c78-8008-ebe74f27291f" />
</class>
<class name="Queue">
<error id="26000" name="GeneralQueueJobFailed"
uid="515b6441-ecb6-4f1e-9a94-28daa9d8bf53"
JobUID="8cabe661-121b-41f4-91e2-a4dc034028d1" ComputerName="WS-PROJ"
GroupType="TimesheetReview" MessageType="ReviewTimesheetMessage"
MessageId="1" Stage="" />

</class>
</general>
</errinfo>
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top