Timesheet Approval - Where to set

M

max

Hi,
I edited timesheet,the resource goes to the timesheet and enters the hours
he has used.
But when he does "submit" it does get updated.and later when he returns to
mainsheet it will be updated and "approval status" says approved.

If i want his manager to approve the timesheet, where in project server
should i go and enable this. I want timesheets to be approved by designated
manger
Thanks
max
 
R

reza

Max...

If you want to set timesheet manager for your resource...
go to resource center...click your resource and in timesheet manager
box...choose your name or your timesheet manager. Save.

But if you want set more than one resources...in resource center
page---click your resources ---- click bulk edit and in timesheet manager
box, choose your name or your timesheet manager. Save.

hope this help you

reza
 
M

max

Thanks a lot for your response Reza.
Though i had seen this didn't know that is where we had to set it
I tried works perfect
max
 