M
mike
Hello, I am having trouble with the timesheet approval process. Most
resources have a timesheet manager setup in User Management. The
Timehsst mangers are in the Resource Managers Group. I only need for
the timesheets to be reviewed by just the timesheet manager, no
further approval is necessary.
The problem is that when I go to approve a timeshst for my resource, i
am prompted to choose the next approver. My timesheet manger is the
owner of the comapany, and he only needs to see my timesheet, not all
of my resources.
How do I stop project server from wanting me to enter the next
approver.
Fixed Approval routing is not checked in Timesheet settings.
Thanks
resources have a timesheet manager setup in User Management. The
Timehsst mangers are in the Resource Managers Group. I only need for
the timesheets to be reviewed by just the timesheet manager, no
further approval is necessary.
The problem is that when I go to approve a timeshst for my resource, i
am prompted to choose the next approver. My timesheet manger is the
owner of the comapany, and he only needs to see my timesheet, not all
of my resources.
How do I stop project server from wanting me to enter the next
approver.
Fixed Approval routing is not checked in Timesheet settings.
Thanks