N
Nab
Is there anyway I can configure MS Project 2007 to send approval request to
multiple project manager? That is, If the resource is working on different
projects and each project have different project manager. s/he needs to fill
the timesheet with number of tasks. To approve their timesheet is it possible
to set the approval process based on the project?
e.g John working on “X†project under Project Manager “ABCâ€, and he also
work on project “Y†supervised by PM “XYZâ€. For all hours he worked on tasks
for project X need approval by PM “ABCâ€, whereas all the hours worked for
Project “Y†need approval from “XYZâ€. Current system allows us to assign each
resource with 1 timesheet supervisor and that does not serve the purpose.
Please suggest any tip or idea how to comply with this requirement. I
appreciate your time and effort.
multiple project manager? That is, If the resource is working on different
projects and each project have different project manager. s/he needs to fill
the timesheet with number of tasks. To approve their timesheet is it possible
to set the approval process based on the project?
e.g John working on “X†project under Project Manager “ABCâ€, and he also
work on project “Y†supervised by PM “XYZâ€. For all hours he worked on tasks
for project X need approval by PM “ABCâ€, whereas all the hours worked for
Project “Y†need approval from “XYZâ€. Current system allows us to assign each
resource with 1 timesheet supervisor and that does not serve the purpose.
Please suggest any tip or idea how to comply with this requirement. I
appreciate your time and effort.