We have installed the EPM 2003 solution (with SP-1) in ou
organizatio
recently
We are facing some problems with the Timesheet remainders

We are getting the message " Your Timesheet has not been submitted fo
the period 13-03-2005 - 19-03-2005 " even though the Timesheet ha
submitted for that period. (The above date is just one example. Ther
are more messages depend on the work assignments on the plan)

Our Tracking settings as follows:

default method for reporting progress on tasks: Hours of work done pe
dayor per wee
Lock down defaults: Force project managers to use the progres
reporting method specified above for all projects
Time period settings: Managed Periods - Allow only Project We
Acces
users to update actual during open period
Managed Timesheet periods: Resources should report their hour
worked every da
 
M

Mark Byington

We went with 'non-managed periods' for that reason. It didn't seem to change
how we want to use the product and it didn't produce those messages any more.

You probably should consult the configuration guide and the administrators
guide to make that decision.
 