Hello,
I have a user (David) who is the timesheet manager of another user
(Alvin). David is in the Resource Manager group, he has to approve
Alvin’s timesheets but he is not required to create timesheets for
himself. I have set David as “can not be assigned as a resource” but
he still has to do timesheets. Is there a way for David not to see his
personal timesheets in the timesheet approval in WebAccess? Or else,
is there a way of preventing the creation of timesheets for David?
I am using Project Server 2007 SP1.
Thanks for your help guys!!
 
D

Dale Howard [MVP]

Barone di Munchausen --

I believe that Microsoft envisions the Timesheet system to be an "all or
nothing" proposition. I am not aware of any default permissions you can
change to exempt David from the Timesheet process. On the other hand,
perhaps someone else has another idea for you. Hope this helps.




Hello,
I have a user (David) who is the timesheet manager of another user
(Alvin). David is in the Resource Manager group, he has to approve
Alvin’s timesheets but he is not required to create timesheets for
himself. I have set David as “can not be assigned as a resource” but
he still has to do timesheets. Is there a way for David not to see his
personal timesheets in the timesheet approval in WebAccess? Or else,
is there a way of preventing the creation of timesheets for David?
I am using Project Server 2007 SP1.
Thanks for your help guys!!
 
J

Jonathan Sofer [MVP]

Who is set as the "Timesheet Manager" for David?

Jonathan

Hello,
I have a user (David) who is the timesheet manager of another user
(Alvin). David is in the Resource Manager group, he has to approve
Alvin’s timesheets but he is not required to create timesheets for
himself. I have set David as “can not be assigned as a resource” but
he still has to do timesheets. Is there a way for David not to see his
personal timesheets in the timesheet approval in WebAccess? Or else,
is there a way of preventing the creation of timesheets for David?
I am using Project Server 2007 SP1.
Thanks for your help guys!!
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top