Hi
(using PS2007, SP1 + PIU)
We intend to use timesheet for time reporting with following settings:
Timesheet period = MONTH
Timesheet Grid Column Units = WEEK
Timesheet units = DAY
I created timesheet for september 2008: once created timeshhet page shows 4
columns (5 days each) and a 5th column (2 days, ie 29/09 & 30/09).
Trouble is that I cannot report (edit) time within 5th column !!!
Is it a bug or normal behaviour? (should the last week be complete? ie also
5 days)
How do we cope with it?
Thanks for your help
jpa
(using PS2007, SP1 + PIU)
We intend to use timesheet for time reporting with following settings:
Timesheet period = MONTH
Timesheet Grid Column Units = WEEK
Timesheet units = DAY
I created timesheet for september 2008: once created timeshhet page shows 4
columns (5 days each) and a 5th column (2 days, ie 29/09 & 30/09).
Trouble is that I cannot report (edit) time within 5th column !!!
Is it a bug or normal behaviour? (should the last week be complete? ie also
5 days)
How do we cope with it?
Thanks for your help
jpa