T
TimS
I have a question regarding tracking time using Project Web Access in
conjunction with Project Server 2007. I have created an Enterprise Project,
built my resources using the Build Team From Enterprise function, generated a
years worth of timesheet periods, assigned detailed tasks to the resources,
published my assignments.
The problem is that if the resources use the "My Timesheets" capability to
enter and submit their time, this time is not reflected in the project
schedule. But, if they use the "My Tasks" function and charge time and
submit it, it is reflected in the project schedule. My preference would be
to use the Timesheet function and not the "My Tasks" function for charging
and submitting time against assigned project tasks.
Can anybody tell me what I am doing wrong, and how to correct it?
Thanks in advance!
Tim
conjunction with Project Server 2007. I have created an Enterprise Project,
built my resources using the Build Team From Enterprise function, generated a
years worth of timesheet periods, assigned detailed tasks to the resources,
published my assignments.
The problem is that if the resources use the "My Timesheets" capability to
enter and submit their time, this time is not reflected in the project
schedule. But, if they use the "My Tasks" function and charge time and
submit it, it is reflected in the project schedule. My preference would be
to use the Timesheet function and not the "My Tasks" function for charging
and submitting time against assigned project tasks.
Can anybody tell me what I am doing wrong, and how to correct it?
Thanks in advance!
Tim