Timesheet Questions

C

Chris

I am running into a problem. I have a project posted to project server.
When I try to fill out timesheet for a task, it only lets me change the
percent complete. However, there has been many times when the actual work is
less than the estimate and I would like to basically enter the actual amount
of time worked and then be able to change the percent complete to 100% so
that the cost is calculated correctly. (I would also like to use this data
somehow to make better estimates in the future).

I changed the settings in the admin to allow entering of actual work and
work remaining, but I still can't edit those fields.

Can someone tell me what I am doing wrong or what is best way to handle this?
 
C

Chris

Brilliant, thanks! I will look through the rest of your FAQ for more gems!



Thanks,


Chris
 
D

Dale Howard [MVP]

Chris --

You are more than welcome, my friend! :) I believe you will find many
treasures on our FAQ site. Also, take a look at the home page of our site
for information about an upcoming training class for Project Server 2003
administrators.
 