C
Chris
I am running into a problem. I have a project posted to project server.
When I try to fill out timesheet for a task, it only lets me change the
percent complete. However, there has been many times when the actual work is
less than the estimate and I would like to basically enter the actual amount
of time worked and then be able to change the percent complete to 100% so
that the cost is calculated correctly. (I would also like to use this data
somehow to make better estimates in the future).
I changed the settings in the admin to allow entering of actual work and
work remaining, but I still can't edit those fields.
Can someone tell me what I am doing wrong or what is best way to handle this?
When I try to fill out timesheet for a task, it only lets me change the
percent complete. However, there has been many times when the actual work is
less than the estimate and I would like to basically enter the actual amount
of time worked and then be able to change the percent complete to 100% so
that the cost is calculated correctly. (I would also like to use this data
somehow to make better estimates in the future).
I changed the settings in the admin to allow entering of actual work and
work remaining, but I still can't edit those fields.
Can someone tell me what I am doing wrong or what is best way to handle this?