A
Andy Novak
I have read Dale Howard's very helpful comments about best practices
in timesheet reporting. Dale, I have a few follow-up questions for
you (or any one else for that matter):
1. You were discussing the % complete method in one thread a while
back but it did not mention entering REM WORK (just task name, actual
start, % work complete, and actual finish). How would you be able to
generate new forecasted finish dates for things that may not have
finished this week but may have gotten behind?
2. When doing time reporting via web, what are ALL the correct
settings under Tools | Options | Calculation ?
3. Anyone used the method where team members enter total hours worked
in the week rather than worked each day? What are the ups and downs
to that?
4. When you use web reporting, regarding the finish dates being
adjusted as a result of a higher/lower rem work figure, by WHAT DATE
are they adjusted? The day the team member enters the data via web,
the day they submit the report, or the day the data is actually
approved and the project files are updated (there could be some lag
time in there)?
5. When we tried web progress reporting in the past, VERY OFTEN the
project data became out of sync with the information in the
timesheets. Almost at the point of being unmanageable. Does one need
to republish frequently in order to keep them in sync? What's the
best way to manage this? Often times I would have team members using
the timesheet as the "plan" (which isn't correct anyway). But it was
so easy for the timesheet to reflect incorrect % complete, etc.,
especially if ANY manual updates were made to the plans.
Thanks,
Andy Novak
University of North Texas
in timesheet reporting. Dale, I have a few follow-up questions for
you (or any one else for that matter):
1. You were discussing the % complete method in one thread a while
back but it did not mention entering REM WORK (just task name, actual
start, % work complete, and actual finish). How would you be able to
generate new forecasted finish dates for things that may not have
finished this week but may have gotten behind?
2. When doing time reporting via web, what are ALL the correct
settings under Tools | Options | Calculation ?
3. Anyone used the method where team members enter total hours worked
in the week rather than worked each day? What are the ups and downs
to that?
4. When you use web reporting, regarding the finish dates being
adjusted as a result of a higher/lower rem work figure, by WHAT DATE
are they adjusted? The day the team member enters the data via web,
the day they submit the report, or the day the data is actually
approved and the project files are updated (there could be some lag
time in there)?
5. When we tried web progress reporting in the past, VERY OFTEN the
project data became out of sync with the information in the
timesheets. Almost at the point of being unmanageable. Does one need
to republish frequently in order to keep them in sync? What's the
best way to manage this? Often times I would have team members using
the timesheet as the "plan" (which isn't correct anyway). But it was
so easy for the timesheet to reflect incorrect % complete, etc.,
especially if ANY manual updates were made to the plans.
Thanks,
Andy Novak
University of North Texas