Timesheet Reporting....

M

Mike Wilson

I need to create a report to show who is using (or not using) the
Timesheet in Project Server Web Access. I created a report that
displayed "Actual Work" by employee, but the problem is that "Actual
Work" can also be entered in by the Project Manager, and does not
necassarily indicate that the employee used the Timesheet to report
their "Actual Work". Any ideas?

-Mike Wilson-
 
G

Gary Chefetz [MVP]

Mike:

In Project Web Access, select Resources > View resource assignments. You can
see whether a resource has submitted an update in this view. Play around
with grouping to get this to look the way you want.
 