Hi,

Is there a way (field or anything) to save the time a team member entered
into the sytsem? Example: teammember enters 6 hours for a task but PM only
want to aprove 4. I want to have 4 hours to be saved into Actual Work but I
want to have the 6 hours recorded somewhere.

kattila
 
M

Marc Soester

Hi kattila,
Sorry, but you are not able to enter 2 different actual values per day in
Project Web Access.
 
T

tonyzink

Hi kattila --

I would say that this is a situation where the PM should send an Email,
pick up the phone, or walk over to the Team Member's desk. If you feel
that an error has been made in the entry of the work hours on the Team
Member's PWA timesheet, then simply ask them to make a correction and
resubmit.

Don't fall into the trap of allowing Project Server to become a
replacement for human-to-human interaction (it's an easy trap to fall
into!).

Good luck!

Tony Zink
========================================
http://www.msprojectreporter.com
http://www.pmreporter.com
http://www.sharepointreporter.com
http://www.msofficereporter.com
http://www.dotnetreporter.com
========================================
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top