D
David F-H
Project Server 2007 (SP1 + Aug Cum hotfixes) & SQL Server 2005
A couple of questions :
Timesheet Manager - When away (on leave, etc), what is the preferred method
of delegating timesheet approvals to someone else ? The best method I can
figure out is to select all of his/her resources (in Resource Center), click
"Bulk Edit" and assign all to a new Timesheet Manager. Is there a better way
?
Project Manager - Can any project manager (or Resource Manager) that has the
ability to open a project (whether they are the project owner or not) also
approve task updates that have been submitted by project team members ? What
will they see in PWA if they go into Task Approvals?
Thanks
A couple of questions :
Timesheet Manager - When away (on leave, etc), what is the preferred method
of delegating timesheet approvals to someone else ? The best method I can
figure out is to select all of his/her resources (in Resource Center), click
"Bulk Edit" and assign all to a new Timesheet Manager. Is there a better way
?
Project Manager - Can any project manager (or Resource Manager) that has the
ability to open a project (whether they are the project owner or not) also
approve task updates that have been submitted by project team members ? What
will they see in PWA if they go into Task Approvals?
Thanks