K
Kaisera
Hi,
We are working with MS-Project Server 2007 - full resoiurce management.
I have 2 problems need to be clarified:
1. When we add an additional resource to an existing task, save & publish
the project, he does not see it in My Tasks / Timesheet views & not able to
add it's line to the timesheets. On the oposite, if a new task is created for
that matter, all goes ok at all places. Why is that? Is there any solution or
workaround?
2. We configured the My Tasks view to display a full week period break into
days (thanks to SP1 as i know). The problem is that each week, the view seems
to show which days it chooses instead of Sunday-to-Saturday week (for
example: it some times show Thursday-to-Wednesday week). Can it be configured?
Thanks,
Yaara.
We are working with MS-Project Server 2007 - full resoiurce management.
I have 2 problems need to be clarified:
1. When we add an additional resource to an existing task, save & publish
the project, he does not see it in My Tasks / Timesheet views & not able to
add it's line to the timesheets. On the oposite, if a new task is created for
that matter, all goes ok at all places. Why is that? Is there any solution or
workaround?
2. We configured the My Tasks view to display a full week period break into
days (thanks to SP1 as i know). The problem is that each week, the view seems
to show which days it chooses instead of Sunday-to-Saturday week (for
example: it some times show Thursday-to-Wednesday week). Can it be configured?
Thanks,
Yaara.