Timesheet Updates Not Showing up on the Updates page for PM"s

J

JodyJ

We've been using Project Server 2003 since the middle of July. We have
several instances (250 rows of data) in which people have entered time but it
never showed up in PWA for a PM to pull in to a project plan.

There was a previous post that discussed a hotfix
(http://support.microsoft.com/kb/893087) however, I've looked at this data
and there are many, many scenarios where the resource did not enter a zero on
their timesheet. If they did, they subsequentlly hit delete. With this many
errors, I'm guessing that this issue goes much further than deleting or
zeroing out a # but I can't find a pattern in the data.

Has anyone else had any success figuring out what the issue is? I'm in a
bit of a crunch here as the only way I have found to "fix" this is to go to
Adjust Actuals, change the hours that aren't updating, change them back to
the original hours and then click Update Actuals....obviously a very tedious
process and not likely to keep the same thing from happening going forward.
 
R

Reid McTaggart

Just a couple ideas you may already have tried:

1) Have the PMs republish their plans and check the box to Become the
manager for these assignments.

2) Have the resources clear out temp files on IE (Tools > Internet Options >
Delete Files.
 
J

JodyJ

Unfortunately, neither of these solutions worked.

Any other ideas? At this point, I'm actually more interested in figuring
out WHY it's happening so that I can prevent it.

We had roughly 1000 hrs of project time that didn't get updated to plans in
just a little over a month. It is shaking our faith in the data project is
giving us tremendously.
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top