H
hinrgsunshine2
In a recent posting, someone asked about configuring mulitple approvers for
tasks.
Dale responded,
"If you are using Project Server 2003, this is not possible. The best
you
can do is to use Managed Time periods, have a Resource Manager approve
timesheets, and then the Project Manager approve the task updates into the
actual Microsoft Project plan."
We're using 2003, managed time periods. We would like to have
resource managers approve timesheets and project managers approve task
updates? Is this something we can configure in 2003 or do we have to
go to 2007?
tasks.
Dale responded,
"If you are using Project Server 2003, this is not possible. The best
you
can do is to use Managed Time periods, have a Resource Manager approve
timesheets, and then the Project Manager approve the task updates into the
actual Microsoft Project plan."
We're using 2003, managed time periods. We would like to have
resource managers approve timesheets and project managers approve task
updates? Is this something we can configure in 2003 or do we have to
go to 2007?