Timesheet view in project server 2007

J

Jani Edmunds

Can you change the timesheet view in project server 2007 (PWA). I would like to have an answer to change the following coloumns as described below?
Remove the comments and the approval status coloumn.
Combine the information from the Task Name and the billing category to one single coloumn with the relevant information.
Can someone please assit.

A Womand Told Me
http://www.awomantoldme.com
 
D

Dale Howard [MVP]

Jani --

No, this is not possible. You cannot remove the default columns in the My
Timesheet view. Hope this helps.
 