Timesheet View in Web Access

S

Savoy55

I am attempting to customize the Timesheet view for 3 projects in my
production Project Server. I had the project managers update their plans
through the Tools > Customize> Published Fields option. This did not place
the columns in the Timesheet View. I do not want to modify the Timesheet View
for everyone by adding the columns to the view. Is there a way to modify the
Sheet for specific projects?
 
D

Dale Howard [MVP]

Savoy55 --

It's an all or nothing deal. You will need to add the additional fields to
the Timesheet view and those columns will be visible to all team members.
Sorry.
 