Timesheet View

P

Prajakta

Hi,
My problem is with current timesheet view.
Current view works in this way:
A resource is assigned task of 8hrs.
Now when he enters the actual work done or remaining work
say 4hrs,The % work complete gets To 50 %.
Now I know this is very true,but pratically it doesn't happens like that.
The resource though worked for 4 hrs ,might not have completed 50% of
work(may be due to some technical reasons),and PM will be under impression
that ok! 50 % of the work got over(pratically its not).
Also problem is if resource worked for more that 8 hrs for that task say
10hrs ,then the original time allocated to that task also get updated to 10
hrs which is not recommended(Well i might be wrong in perception,but as far
as i know it works the same).
Now I want to change view such that
resource should enter actual hrs of working and aslo the actual % of work
completed in those hours.
E.g
If task is of 8Hrs
And resource worked for 4 hrs and he completes only 30 % of work in those 4
hrs.
Also it should get reflected in the schedule.
Is it possible?
I tried it using enterprise feilds but it does not get reflected in the
schedule.

Please help me on this.

Thanx and regards
Prajakta...
 
G

Gary L. Chefetz [MVP]

Prajakta:

If you're collecting hours worked, you should teach your users to adjust the
remaining work value. You have a choice to collect work and remaining work,
or you can collect percent complete and remaining work. You can't adjust
both work and percent complete.

You also need to set a baseline if you want to preserve the original work
value as Work always = Actual Work, once actual work has consumed or
exceeded the original planned work value.
 