timesheet views

J

JonnoMo

Hi All

Any one know if it is possible to change the time sheet view in PWA of days
to show Mon. Tues, Wed etc and to grey out sat sun just like in Microsoft
Project

As my developers find it very hard to use visulally .... ;0)

Any help views etc appreciated....

JMo
 
D

Dale Howard [MVP]

JMo --

You can change the display of the timesheet to show the day and date (such
as Tues 30) by completing the following steps:

1. Log into PWA with administrator permissions
2. Click Admin - Customize Project Web Access
3. In the Time Period Settings section, set the "Number of weeks spanned"
value to 1
4. Click the Save Changes button

I do not know of any default method to shade the Saturdays and Sundays with
a different background color, such as gray. Hope this helps.
 
J

Joel P.

This option appears to only be available for "Non-Managed Time Periods". We
use Managed Time Periods. Yet we want to move to monthly time periods. Is
this possible?

Joel
 
D

Dale Howard [MVP]

Joel --

If you use Managed Time Periods, then the only way to achieve what I
proposed is if you use weekly time periods. Hope this helps.
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top