S
Studer
I'm using MsP Professional 2003 with SP3 and MsP Server 2003
For several of my resources, some tasks aren't shown in their
timesheet/"View my tasks". It became obvious when they were checking the
Gantt Charts of the projects they are working on and when swiching to their
timesheet, some projects with their tasks didn't show up.
I've tried:
- republishing the projects
- the "Tasks displayed" on "View my tasks" are "All tasks"
- there are no filters on the tasks
They are team members of these projects, their tasks in the missing projects
aren't finished, I simply cant' find a reason for this.
Any ideas?
Thank you.
Studer
For several of my resources, some tasks aren't shown in their
timesheet/"View my tasks". It became obvious when they were checking the
Gantt Charts of the projects they are working on and when swiching to their
timesheet, some projects with their tasks didn't show up.
I've tried:
- republishing the projects
- the "Tasks displayed" on "View my tasks" are "All tasks"
- there are no filters on the tasks
They are team members of these projects, their tasks in the missing projects
aren't finished, I simply cant' find a reason for this.
Any ideas?
Thank you.
Studer