Timesheet vs Project Center

S

Studer

I'm using MsP Professional 2003 with SP3 and MsP Server 2003

For several of my resources, some tasks aren't shown in their
timesheet/"View my tasks". It became obvious when they were checking the
Gantt Charts of the projects they are working on and when swiching to their
timesheet, some projects with their tasks didn't show up.

I've tried:
- republishing the projects
- the "Tasks displayed" on "View my tasks" are "All tasks"
- there are no filters on the tasks

They are team members of these projects, their tasks in the missing projects
aren't finished, I simply cant' find a reason for this.

Any ideas?

Thank you.

Studer
 
D

Dale Howard [MVP]

Studer --

Open the project(s) in question and click Tools - Build Team from
Enterprise. Are the team members with the missing tasks set as Proposed in
the Type column? If so, set them to Committed. Then click Collaborate -
Publish - All Information. Let us know if this helps.
 