timesheet

J

Janett

I would like that the resource place the actual hrs and the actual start date
in the server However right now they can only input actual hrs and remaining
hrs
 
R

Rod Gill

Hi,

If you are entering hours per day, then the first day with Actual hours
becomes the Actual Start date.
 
D

Dale Howard [MVP]

Janett --

From your description, it sounds like your organization is using the Actual
Work Done and Work Remaining method of tracking. In this method, users
enter data in only the Actual Work and Remaining Work fields on he PWA
timesheet page. As you have discovered, this method of tracking is not date
sensitive, which means that it cannot show a late start for a task.

To add the Actual Start field to each user's timesheet in PWA, your Project
Server administrator will first need to add the Actual Start column to the
Timesheet view in PWA (click Admin - Manage Views in PWA). After doing
this, your project managers will then need to add the Actual Start field to
the list of published fields in EVERY project they manage by completing the
following steps:

1. Open an enterprise project
2. Click Tools - Customize - Published Fields
3. Add the Actual Start field to the list on the right
4. Click the OK button
5. Click Collaborate - Publish - Republish Assignments
6. Click the OK button
7. Save and close the project

Again, I want to emphasize that your EVERY one of your PM's must complete
the above seven steps for EVERY project that they manage. After everyone
does the required steps, your team members will be able to set the Actual
Start date, plus enter Actual Work and Remaining Work on each task in their
PWA timesheets. Hope this helps.
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top