Hi;
I am admin of msp server 2007.
I need to define two different type of timesheet for two different
resources. because they use different calanders.what can i do?
and i define a new timesheet classification.how can i delete it after saving?
 
R

Ravi

Hi;
I am admin of msp server 2007.
I need to define two different type of timesheet for two different
resources. because they use different calanders.what can i do?
and i define a new timesheet classification.how can i delete it after saving?

Hi Shima,

If your resources are to use different calendar, you can define
resource calendars and set them to use single timesheet.
Is that not what you would be needing with those two resources?

Thanks,
Ravi.
 
J

Jonathan Sofer

Shima,

I'm not sure exactly what you mean in your first question but I can answer
your second question. In MSPS 2007 you cannot delete a timesheet
classification after you created and saved it. You can only inactivate.
The same goes for creating new administrative line items. This is a bug in
MSPS 2007.

Jonathan
 