M
MartynF
I have looked all over for help in understanding a couple of issues, here
and elsewhere, to no avail. I think to myself "if only Fixed Duration meant
Fixed Duration rather than Sort of Fixed Some of the Time"...
We have Project Server 2007 SP2 and Project Professional SP2 and I run the
PMO such as it is here.
Aside from IT projects, I create a "Support Activity project" with tasks for
various support and maintenance activities. When planning ahead, the work
and assignment time is estimated but the requirement is to report and plan
on a monthly basis. A resource might be "planned" to spend 40% of time on a
support activity in month 1 but only 20% in month 2, etc. so I create Fixed
Duration Tasks for these - of a one month duration and not effort driven.
Users use the timesheet completion and import functionality to update the
hours spent on the "monthly task" on a weekly timesheet basis.
My issues are:
1. As the tasks get updated with actual hours spent, sometimes the Fixed
Duration task changes duration extending beyond the month end. I can not for
the life of me work out why? I think it is when the actual work numbers
reported weekly are less than the inital schedule says. e.g. the planned
schedule says resource1, week 1, 10 hours, resource 1, week 2 10 hours etc.
but only 2 hours gets reported in week 1 as actual work. What seems to
happen is the Project takes the initial "planned work" as Fixed Work and
changes the duration to match the assignment rate. I need the server to
respect the fixed duration and at least prompt whther or not to changed the
planned work total or planned assignment rate. If I adjust the schedule
manually I get these options via the smart tag.
2. Almost as a reverse, in the above case if resource 1 reported spending
all 40 hours on the activity in week 1 Project would automatically mark the
task as complete. but of course it may not be - only the duration should be
fixed, not the work. The plan is only a plan. Why cannot project server
respect the fixed duration and understand that more work may be necessary
and adjust the assignment rate or planned work for the monthly task?
I'm sorry if this is confusing but I am on the point of ditching Project
Server completely.
Martyn Forbes
and elsewhere, to no avail. I think to myself "if only Fixed Duration meant
Fixed Duration rather than Sort of Fixed Some of the Time"...
We have Project Server 2007 SP2 and Project Professional SP2 and I run the
PMO such as it is here.
Aside from IT projects, I create a "Support Activity project" with tasks for
various support and maintenance activities. When planning ahead, the work
and assignment time is estimated but the requirement is to report and plan
on a monthly basis. A resource might be "planned" to spend 40% of time on a
support activity in month 1 but only 20% in month 2, etc. so I create Fixed
Duration Tasks for these - of a one month duration and not effort driven.
Users use the timesheet completion and import functionality to update the
hours spent on the "monthly task" on a weekly timesheet basis.
My issues are:
1. As the tasks get updated with actual hours spent, sometimes the Fixed
Duration task changes duration extending beyond the month end. I can not for
the life of me work out why? I think it is when the actual work numbers
reported weekly are less than the inital schedule says. e.g. the planned
schedule says resource1, week 1, 10 hours, resource 1, week 2 10 hours etc.
but only 2 hours gets reported in week 1 as actual work. What seems to
happen is the Project takes the initial "planned work" as Fixed Work and
changes the duration to match the assignment rate. I need the server to
respect the fixed duration and at least prompt whther or not to changed the
planned work total or planned assignment rate. If I adjust the schedule
manually I get these options via the smart tag.
2. Almost as a reverse, in the above case if resource 1 reported spending
all 40 hours on the activity in week 1 Project would automatically mark the
task as complete. but of course it may not be - only the duration should be
fixed, not the work. The plan is only a plan. Why cannot project server
respect the fixed duration and understand that more work may be necessary
and adjust the assignment rate or planned work for the monthly task?
I'm sorry if this is confusing but I am on the point of ditching Project
Server completely.
Martyn Forbes