C
CC
Good day,
I would like to know in general what the best practices are in terms of
using timesheets and task updates in the Project Server 2007 environment.
Is it recommended that team members fill in timesheets and then import into
My Tasks or should team members update task status before creating their
timesheets.
If team members are updating timesheets and the importing timesheet data
into tasks, what type of updates to the project plan should be avoided and
what type of updates should be safe. Will the application be able to resolve
instances where the assignments changes while tasks are in progress and
timesheets have been created but not submitted?
Thank you.
I would like to know in general what the best practices are in terms of
using timesheets and task updates in the Project Server 2007 environment.
Is it recommended that team members fill in timesheets and then import into
My Tasks or should team members update task status before creating their
timesheets.
If team members are updating timesheets and the importing timesheet data
into tasks, what type of updates to the project plan should be avoided and
what type of updates should be safe. Will the application be able to resolve
instances where the assignments changes while tasks are in progress and
timesheets have been created but not submitted?
Thank you.