We need to display additional information about tasks in timesheets
dialog, so I created task text Custom property - I fill in same
information in project plan, and I configured that this field will be
displayed in timesheets.

My Problem is that value entered in project plan isn't displayed.

I deleted timesheets and then created timesheets again but result is
the same.

Users can see collumn with my custom property but only blank text is
displayed there.


Regards Martin Winzig
 
D

Dale Howard [MVP]

winzigm --

What version of Project Server are you using? 2002, 2003, or 2007? It
sounds like 2007, so I will give you a 2007 answer. When you created the
custom task text field, did you remember to select the "Roll down..." option
in the Calculation for Assignment Rows section of the New Custom Field page?
If not, do that and let us know if this helps.
 
W

winzigm

My problem was that timesheets webpart displaying Assignment custom
field :) and not task custom field.
 