Carlos --
In the world of project management using Microsoft Project, the project
communication life cycle looks something like this:
1. Project manager creates project plan with tasks and resources assigned
to those tasks
2. Project manager publishes the project to PWA so that his/her team
members know what tasks they are supposed to do and when they are supposed
to perform the tasks
3. Each week (ideally), the team members gather their Actual Work and
Remaining Work for the tasks on which they have worked
4. At the end of each week, team members submit their "actuals" to their
project manager
5. Project manager updates the actuals into each project plan
6. Project manager analyzes the project to determine the current state of
the project in relation to the actual work submitted
7. Project manager publishes the latest changes in the project to PWA
The timesheet is used in steps #3 and #4 to report their Actual Work and
Remaining Work values.
Now, Carlos, let me ask you a question: Are you familiar with the formal
discipline of project management? The nature of your questions makes me
think that his is a new world to you. If that is the case, you will become
more valuable to your company as its Project Server administrator if you
would start learing as much as you can about project management. You might
start with the Project Management Institute (
www.pmi.org) as a source of
reading material on project management.
Hope this helps.