A
AndyS
Hi
I have noticed very strange and worrying things happening to resource's
timesheets where actual time is appearing in timesheets automatically in
future timesheets and also in the existing, submitted timesheets.
For example looking at my timesheet for week 10, 2008 shows 26h total in the
'my timesheets' list view in PWA but when I click on the 'my timesheet' link
the actual time amounts in the timesheet add up to 57.25 hours with a task
that I haven’t booked to appearing with actual time matching planned time.
I suspect that this time has appeared in timesheets from project
professional where 'actual work' values have been specified for tasks, and as
a result of the changes due to SP2 changes deleted or new tasks are appearing
in timesheets automatically. Are my suspicions correct on this is, project
assignments altering the actual values in timesheets, if so how can this be
undone and prevented in future.
If I’m not correct in my assumption that this comes from ‘Actual Work’ in
project plans could anyone give me some clues as to how this time is
automatically appearing in resource’s timesheets.
The result of these automatic changes could be disasterous, records of time
spent on projects would not be accurate and billing to customers will be
incorrect unless we can be assured that the information in timesheets has
been put there by the resource and not by some other means.
Thanks in advance
Andrew
I have noticed very strange and worrying things happening to resource's
timesheets where actual time is appearing in timesheets automatically in
future timesheets and also in the existing, submitted timesheets.
For example looking at my timesheet for week 10, 2008 shows 26h total in the
'my timesheets' list view in PWA but when I click on the 'my timesheet' link
the actual time amounts in the timesheet add up to 57.25 hours with a task
that I haven’t booked to appearing with actual time matching planned time.
I suspect that this time has appeared in timesheets from project
professional where 'actual work' values have been specified for tasks, and as
a result of the changes due to SP2 changes deleted or new tasks are appearing
in timesheets automatically. Are my suspicions correct on this is, project
assignments altering the actual values in timesheets, if so how can this be
undone and prevented in future.
If I’m not correct in my assumption that this comes from ‘Actual Work’ in
project plans could anyone give me some clues as to how this time is
automatically appearing in resource’s timesheets.
The result of these automatic changes could be disasterous, records of time
spent on projects would not be accurate and billing to customers will be
incorrect unless we can be assured that the information in timesheets has
been put there by the resource and not by some other means.
Thanks in advance
Andrew