timesheets pending approval

M

mmtang

We are getting these messages on the home page: "You have 1 timesheets
pending approval for the period ...." Clicking on the message returns
the following message: "Your resources have not submitted any timesheet

changes for this period." I've tried navigating through all the time
periods with no luck.

When I query the database for timesheets pending approval, i can see
that there is 1 task that needs to be approved (select *from
MSP_WEB_ASSIGNMENTS
where WASSN_ACTUALS_PENDING =1); however the task no longer exists.
I've tried re-publishing the plan with no luck. When I delete the
project, the message still appears on the homepage. The query select
*from MSP_WEB_ASSIGNMENTS where WASSN_ACTUALS_PENDING =1 returns 4
projects now. Any ideas?
 
M

Mike Glen

Hi ,

Try posting on the server newsgroup as this one is closing down. Please see
FAQ Item: 24. Project Newsgroups. FAQs, companion products and other useful
Project information can be seen at this web
address:http://project.mvps.org/faqs.htm .

Mike Glen
Project MVP
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top