T
TommyF
Hi!
When I'm working on one and the same project twice a day (8:00-10:00 and
14:00-16:00) it is only possible to enter 4h working time for that day and
that project.
Is it possible to split this work-time so that it is possible to see in the
report when exactly I was working on a project? 4h is too unexact for our
requirements.
Thanks a lot!
Best regards,
Thomas Fluch!
We have:
MS Project 2007
MS Project Server 2007
MS Sharepoint Server 2007
MS Office 2003
Active Directory
MS Office Web Access
When I'm working on one and the same project twice a day (8:00-10:00 and
14:00-16:00) it is only possible to enter 4h working time for that day and
that project.
Is it possible to split this work-time so that it is possible to see in the
report when exactly I was working on a project? 4h is too unexact for our
requirements.
Thanks a lot!
Best regards,
Thomas Fluch!
We have:
MS Project 2007
MS Project Server 2007
MS Sharepoint Server 2007
MS Office 2003
Active Directory
MS Office Web Access