Hi;
1)i am using msp server 2007 as an administrator.i'd want my resources to
enter their work in timesheets as hours and minutes for example 3:45 or
3h,45min(minutes is important for me).plz tell me how can i set this?now i
understand that i can enter work just as hours OR minutes for ex: 3h or
180min.is it true?
2)is it neccessary to install outlook add-in for alarms and reminders?my
organisation cant use outlook because of security!plz tell me the usage of
outlook in msp server?
3)can i update my projects just by my resources timesheets without need to
import tasks to timesheets and submit them by my resources?
1)i am using msp server 2007 as an administrator.i'd want my resources to
enter their work in timesheets as hours and minutes for example 3:45 or
3h,45min(minutes is important for me).plz tell me how can i set this?now i
understand that i can enter work just as hours OR minutes for ex: 3h or
180min.is it true?
2)is it neccessary to install outlook add-in for alarms and reminders?my
organisation cant use outlook because of security!plz tell me the usage of
outlook in msp server?
3)can i update my projects just by my resources timesheets without need to
import tasks to timesheets and submit them by my resources?