T
Tina Marie
Hi ...
I have a project where I am using 2 different calendars ... one is 7 days a
week from 8 to 6 1/2 hour lunch and the other is 5 days a week 7 to 5 1 hour
lunch ... I put the 'most common' calendar in as the 'project calendar' and
then for any individual tasks that required the 2nd calendar, I applied it as
a 'task calendar' ... and yet when you turn on time on the start and end
columns, you do not see the time change ... the durations go into decimals
(and I have the tools/options/calendar tab in sync with the project calendar)
.... am I doing something wrong or is there a sequence of events?
The other alternative was to break the project down into 2 small projects
and let them have their own calendars as project calendars and then bring
them together in a consolidated project?
Any suggestions would be appreciated ... thanks, Tina
I have a project where I am using 2 different calendars ... one is 7 days a
week from 8 to 6 1/2 hour lunch and the other is 5 days a week 7 to 5 1 hour
lunch ... I put the 'most common' calendar in as the 'project calendar' and
then for any individual tasks that required the 2nd calendar, I applied it as
a 'task calendar' ... and yet when you turn on time on the start and end
columns, you do not see the time change ... the durations go into decimals
(and I have the tools/options/calendar tab in sync with the project calendar)
.... am I doing something wrong or is there a sequence of events?
The other alternative was to break the project down into 2 small projects
and let them have their own calendars as project calendars and then bring
them together in a consolidated project?
Any suggestions would be appreciated ... thanks, Tina